The types of infrastructure that are included in the rural infrastructure RAMA for the Western Division and Central Region is unlimited. However the Regulation specifies maximum clearing or buffer distances for the construction, operation and maintenance of the following specified types of infrastructure: 

Clearing type

Distance

Permanent fence

20 metres either side - adjoining landholder agreement is required

Access trail

30 metres total width of clearing

Cut line for stock movement

30 metres total width of clearing

Road

30 metres total width of clearing

Telephone Line or cable

30 metres total width of clearing

Power line or cable

30 metres total width of clearing

Drain to water storage

30 metres total width of clearing

Bore drain

30 metres total width of clearing

Pipeline

30 metres total width of clearing

Irrigation channel

30 metres total width of clearing

Firebreak, except where mallee species predominate

30 metres total width of clearing

Airstrip

Distance & area sufficient to meet civil aviation standards

House

5 hectares total area of clearing

Shearing or machinery shed

5 hectares total area of clearing

Ground tank

5 hectares total area of clearing

Dam

5 hectares total area of clearing

Stockyards

5 hectares total area of clearing

Clearing for buildings, windmills and bores is also permitted but only to the minimum extent necessary.

Central Region rural infrastructure clearing distances and areas

Clearing type

Distance

Permanent boundary fence

10 metres either side - adjoining landholder agreement is required

Permanent internal fence

10 metres total width of clearing

Temporary Fence

3 metres total width of clearing

Road or track

6 metres total width of clearing

Airstrip

Distance & area sufficient to meet civil aviation standards

Clearing for dams, buildings, windmills, bores and stockyards is also permitted but only to the minimum extent necessary.

Coastal Region rural infrastructure clearing distances and areas

The types of rural infrastructure that are RAMAs in the Coastal Region are specified in the Regulation and are limited to the construction, operation and maintenance of the following:

Clearing type

Distance

Permanent boundary fence

6 metres either side - adjoining landholder agreement is required

Permanent internal fence

6 metres total width of clearing

Temporary fence

3 metre total width of clearing

Road or track

6 metres total width of clearing

Pipeline

3 metres total width of clearing

Shearing or machinery shed

20 metres from outer edge of the structure

Ground tank

15 metres from outer edge of the structure

Tank (other than a ground tank)

3 metres from outer edge of the structure

Dam

15 metres from outer edge of the structure

Stockyards

20 metres from outer edge of the structure

Bore

10 metres from outer edge of the structure

Pump

3 metres from outer edge of the structure

Water point

3 metres from outer edge of the structure

Windmill

10 metres from outer edge of the structure

Map of the Western Division and Central and Coastal regions in NSW

Map of the Western Division and Central and Coastal regions in NSW

 


Rural infrastructure clearing distances and areas for small holdings and land zoned rural-residential or large lot residential

The types of rural infrastructure that are RAMAs on small holdings and on land in an area zoned as rural-residential or large lot residential are specified in the Regulation and are limited to the construction, operation and maintenance of the following:

Clearing type

Distance

Permanent boundary fence

6 metres either side - adjoining landholder agreement is required

Permanent internal fence

6 metres either side

Temporary fence

3 metre total width of clearing

Road or track

6 metres total width of clearing

Pipeline

3 metres total width of clearing

Buildings other than habitable buildings

20 metres from outer edge of the structure

Windmill

10 metres from outer edge of the structure

Bore

10 metres from outer edge of the structure

Tank

3 metres from outer edge of the structure

Dam

15 metres from outer edge of the structure

Stockyards

20 metres from outer edge of the structure

Pump

3 metres from outer edge of the structure

Water point

3 metres from outer edge of the structure

Protected riparian land

The types of rural infrastructure and the maximum clearing distances and areas are different for protected riparian land. Protected riparian land is land within, or within 20 metres of the bed or bank, of a prescribed stream.

Clearing for rural Infrastructure on protected riparian land is subject to the following limits due to its environmental sensitivity:

Clearing type

Distance

Maintenance of safety clearances around electricity transmission lines

15 metres (where clearing is carried out by an employee of or contractor to a local government or electricity supply authority)

Fencing (other than boundary fence)

6 metres total width of clearing

Boundary fence 6 metres either side - adjoining landholder agreement is required

Farm road

6 metres total width of clearing