All works set out in the Proposal must be completed by the deadlines specified below:
Works |
Deadline |
T1. Undertake data gap investigation.
|
Completed the data gap investigation and submitted a final Data Gap Investigation Report by end of September 2010 |
T2. Conduct a HHERA (including submit draft and final HHERA reports).
|
Completed the HHERA by mid-August 2010,submitted the draft HHERA Report within 3 weeks of receipt of final Site Auditor comments, and submitted the final HHERA Report within 4 weeks of receipt of EPA comments on the draft HHERA Report
|
T3. Undertake ex-situ stabilisation treatability trial (i.e., laboratory scale treatability trial) (including submit the Ex-Situ Stabilisation Treatability Trial Report to the EPA).
|
Completed by June 2010 and submitted the report within 6 weeks of finalisation of the Headland Park HHERA and Headland Park Remedial Action Plan
|
T4. Undertake S-ISCO bench scale trials.
|
Completed by end of June 2010.
|
T5. Prepare and submit draft RAP(s).
|
Submitted within 6 weeks submitting the final HHERA Report (see T2)
|
T6. Submit final RAP(s) to the EPA.
|
Within 8 weeks of receipt of EPA comments on the draft RAP(s)
|
T7. Undertake SEPR and S-ISCO pilot trials (including submit final S-ISCO pilot trials report to the EPA). |
Completed within 23 weeks following issue of relevant approvals and permits to allow the S-ISCO pilot trials to be undertaken
|
T8. Obtain EPA approval on the remedial strategy. |
Approval to be obtained within EPA timeframe
|
T9. Prepare and submit a draft RWP.
|
Submitted within 5 weeks of T8
|
T10. Submit a final RWP to the EPA.
|
Within 8 weeks of receipt of EPA comments on the draft RWP
|
The deadlines for the remedial works will be set out in phase 2.
The EPA must be provided with the following reports by the deadlines specified below:
Report |
Date submitted/to be submitted |
R1. Sampling Analysis and Quality Plan (AECOM Australia Pty Ltd, July 2010)
|
Early July 2010
|
R2. Voluntary Management Proposal Workplan: Data Gap Investigation and Remediation Design Works, EPA Declaration Area 21122 (AECOM Australia Pty Ltd, 6 July 2010)
|
Early July 2010 |
R3. Final Data Gap Investigation Report – EPA Declaration Area, AECOM, 23 September 2010 |
End of September 2010
|
R4. Final Ex-Situ Stabilisation Treatability Trial Report
|
Within 6 weeks of finalisation of the Headland Park HHERA and Headland Park RAP
|
R5. Draft HHERA Report
|
Within 3 weeks of receipt of final Site Auditor comments
|
R6. Final HHERA Report
|
Within 4 weeks of receipt of EPA comments on draft HHERA Report
|
R7. Final S-ISCO Pilot Trials Report
|
Within 23 weeks following issue of relevant approvals and permits to allow the S-ISCO pilot trials to be undertaken
|
R8. Draft RAP(s) including the Site Auditor’s comments
|
Within 6 weeks of submitting the Final HHERA Report
|
R9. Final RAP(s)
|
Within 8 weeks of receipt of EPA comments on draft RAP
|
R10. Draft RWP(s) including the Site Auditor’s comments
|
Within 5 weeks of EPA approval of the remedial methodology (see T8)
|
R11. Final RWP(s) |
Within 8 weeks of receipt of EPA comments on draft RWP |
The reports
relating to the remedial works that will be undertaken during phase 2 and the
deadlines
for their submission to the EPA will be set out under a separate voluntary
management proposal.