2025–26

Funding for these projects came from the Australian Government’s Emergency Response Fund.

The NSW Flood Recovery and Resilience Grant Program funded 15 projects totalling $6,889,160.

Overview
Grant recipient/local government areaProject nameFunding awarded
Bayside CouncilBotany Lane – flood mitigation project$987,257
Bayside CouncilBaxter Road – flood mitigation project$1,008,053
Coffs Harbour City CouncilNorth Boambee detention basin$2,018,784
Fairfield City CouncilHassall Street detention basin upgrade$300,000
Hawkesbury City CouncilScoping studies for voluntary purchase and voluntary house raising$160,000
Hawkesbury City CouncilStage 1 feasibility study and concept design of road improvements to assist flood evacuation$196,000
Hornsby Shire CouncilProposed Galston major drainage upgrade – section A$1,006,666
Inner West CouncilWhites Creek upgrade feasibility study$160,001
Inner West CouncilJarvie Park investigation and design$166,666
Lismore City CouncilLismore flood prediction and warning system review$53,333
Nambucca Valley CouncilEast Macksville levee investigation and flood infrastructure upgrades$99,066
Northern Beaches CouncilShore up: Empowering the Northern Beaches for future disasters$126,667
Penrith City CouncilPenrith central business district flood mitigation works$252,000
Penrith City CouncilOxley Park basin upgrade – investigation and detail design$248,000
Tweed Shire CouncilTweed Lower coastal creeks gauge network augmentation$106,667
Project summaries

Bayside Council

Bayside Council has been awarded funding for 2 projects.

Botany Lane flood mitigation project

This project will improve flood resilience at Botany Lane and surrounding areas in Mascot through upgrades to local drainage infrastructure. Identified as a high flood-risk area in the Mascot Drainage Upgrade and Feasibility Study, the works will address key hydraulic constraints within the broader drainage network to reduce flooding impacts on local roads, businesses and residential properties.

Baxter Road flood mitigation project

This project will reduce flood risk for Baxter Road, Robey Street and nearby areas by upgrading stormwater infrastructure in line with the Mascot Drainage Upgrade feasibility investigations. The works will involve duplicating an existing 1200mm stormwater pipe to improve drainage capacity, reduce flood levels and enhance flood resilience across the local road network.

Coffs Harbour City Council

North Boambee detention basin

This project will implement a key flood mitigation measure identified in the Boambee–Newports Creek Floodplain Risk Management Plan by delivering a detention basin and levee in the North Boambee Valley. The works will reduce flood levels across surrounding industrial areas, the Pacific Highway and the Coffs Harbour Health Campus, improve flood conveyance and significantly reduce expected flood damages in the catchment.

Fairfield City Council

Hassall Street detention basin upgrade

This project will investigate and upgrade the Hassall Street detention basin in the upper Prospect Creek catchment to improve flood safety and reduce downstream flood risk. Following recent dam break and consequence assessments, the works will address capacity and safety requirements to better manage large flood events in a heavily urbanised catchment.

Hawkesbury City Council

Hawkesbury City Council has been awarded funding for 2 projects.

Scoping studies for voluntary purchase and voluntary house raising

This project will assess the feasibility of voluntary purchase and voluntary house raising programs for flood-prone properties in high-risk areas of the Hawkesbury local government area. The study will identify suitable properties and inform future mitigation actions aimed at reducing flood risk and improving community safety.

Feasibility study and concept design of road improvements to assist flood evacuation

This project will investigate road upgrades at key locations to improve flood immunity, trafficability and evacuation efficiency during flood events. The study will assess feasibility and develop concept designs for prioritised local roads to enhance evacuation timeframes and improve access across the Hawkesbury floodplain.

Hornsby Shire Council

Galston major drainage upgrade – Section A

This project will deliver priority drainage upgrades in Galston Village identified in the Hornsby Floodplain Risk Management Study and Plan. Works will address undersized stormwater infrastructure and constrained overland flow paths to reduce flood risk, improve drainage performance and strengthen community resilience to future flood events.

Inner West Council

Whites Creek upgrade feasibility study

This project will investigate upgrade options for Whites Creek, a major drainage corridor affecting Stanmore, Leichhardt and Annandale. The study will identify constraints, develop concept designs and assess costs to improve flood conveyance, reduce property flooding and inform future investment in major drainage infrastructure.

Jarvie Park investigation and design

This project will investigate and design stormwater upgrades within Jarvie Park, Marrickville, to divert flows directly to the Sydney Water network. The works aim to reduce flood pressures in the Marrickville Valley drainage system and align with flood mitigation measures identified in the Marrickville Flood Risk Management Study and Plan.

Lismore City Council

Lismore flood prediction and warning system review

This project will review existing flood prediction and warning systems across the Lismore local government area. The review will identify gaps and recommend improvements to enhance early warning capability and support timely community response during flood events.

Nambucca Valley Council

East Macksville levee investigation and flood infrastructure upgrades

This project will deliver investigation and design for a proposed levee along River Street in East Macksville, along with upgrades to floodgate controls and creek conveyance. The works will reduce flood impacts, improve evacuation times and strengthen flood response and protection for the local community.

Northern Beaches Council

Shore Up: Empowering the Northern Beaches for Future Disasters

This project will develop updated operating strategies for Manly Lagoon, Narrabeen Lagoon and Manly Dam to improve flood mitigation outcomes. The strategies will enable more flexible lagoon openings and dam pre-releases to maximise flood storage, reduce downstream flood levels and enhance community resilience to flooding.

Penrith City Council

Penrith CBD flood mitigation works

This project will develop detailed designs for priority stormwater upgrades within the Penrith central business district, as identified in the Penrith Floodplain Risk Management Study and Plan. The works will reduce flooding to properties and infrastructure and prepare shovel-ready designs for future construction.

Oxley Park basin upgrade – investigation and detailed design

This project will investigate and design upgrades to the Oxley Park detention basin to increase flood storage capacity and improve downstream flood protection. The works will enhance basin safety, formalise spillway arrangements and reduce flood risks to nearby properties, roads and community facilities.

Tweed Shire Council

Tweed Lower coastal creeks gauge network augmentation

This project will expand the flood gauge network in the lower coastal creeks catchments of Tweed Shire, including Cudgen, Cudgera and Mooball creeks. Additional rain and stream gauges will improve flood intelligence, support future warning systems, and increase community awareness for areas such as Wooyung, Pottsville, Hastings Point, Bogangar and South Kingscliff. The upgrade responds to widespread flooding in 2022 and strong community demand for early warning services. Opportunities to adopt or relocate orphaned gauges will also be explored to maximise efficiency and reduce costs.

2023–24

Funding for these projects came from the Australian Government’s Emergency Response Fund.

The NSW Flood Recovery and Resilience Grant Program funded 11 projects totalling $5,352,500.

Overview
Grant recipient/local government areaProject nameFunding
Bayside CouncilSeaforth Park detention basin detailed design$135,000
Bellingen Shire CouncilLavenders Bridge replacement – investigation and design$365,000
Byron Shire CouncilBillinudgel rail bridge debris options study and implementation$175,000
Clarence Valley CouncilPenstock valves – Grafton and South Grafton$50,000
Georges River CouncilDetailed feasibility study – Gloucester Road, Stoney Creek Road and Morgan Street$135,000
Northern Beaches CouncilNarrabeen Lagoon entrance clearance project 2025$1,125,000
Queanbeyan-Palerang Regional CouncilBungendore overflow channel$2,250,000
Shellharbour City CouncilJock Brown detention basin – detailed design$135,000
Tweed Shire CouncilMurwillumbah central business district levee spillway upgrade – detailed design$135,000
Upper Hunter Shire CouncilAberdeen levee rehabilitation$105,000
Wollongong City CouncilUrsula Road flood mitigation scheme (stage one – high priority): construction$742,500
Project summaries

Bayside Council

Seaforth Park detention basin detailed design

This project involves a feasibility investigation and preparation of a detailed design that will result in construction ready drawings for the Seaforth Park detention basin in the Muddy Creek catchment, as recommended in the Bayside west floodplain risk management study and plan.

The proposed basin will be a tiered configuration, with a total capacity of 5,000 cubic metres. It will reduce flooding in a number of properties along its 500-metre flow path.

Bellingen Shire Council

Lavenders Bridge replacement – investigation and design

This project will encompass investigation and design for a replacement of Lavenders Bridge in Bellingen. Lavenders Bridge crosses the Bellinger River and connects South Bellingen and North Bellingen. The existing Lavenders Bridge is a timber/concrete composite bridge that is regularly overtopped by flood water.

This project will involve assessing replacement options, a detailed survey, geotechnical investigation, preliminary design drawings, a construction bill of quantities and cost estimate of the preferred configuration.

Byron Shire Council

Billinudgel rail bridge debris options study and implementation

This project will undertake an options study for debris control measures for the Billinudgel railway bridge. This action is a high priority within the North Byron floodplain risk management plan. The options study will include potential infrastructure improvements and recommended solutions.

Clarence Valley Council

Penstock valves – Grafton and South Grafton

Penstocks are one element of critical infrastructure that prevents flooding in Grafton and there are 24 penstock valves.

Council relies on staff that reside in Grafton to access this flood prevention infrastructure, to provide the required assistance during flood events. It currently takes 4 staff over an hour to shut one penstock, using a large heavy metal wheel.

This project aims to modernise, provide efficiencies and increase safety to the process of shutting penstocks, by installing motorised actuators on them. This will enable activation by pressing a button to close the penstocks.

Georges River Council

Detailed feasibility study – Gloucester Road, Stoney Creek Road and Morgan Street

In 2023, Georges River Council completed an overland flow floodplain risk management study and plan, which covers Gloucester Road, Stoney Creek Road and Morgan Street at Beverly Hills. The community in these areas experienced significant flooding in 2021 and 2022.

This project involves a detailed feasibility study of the option to augment the drainage culverts under Stoney Creek Road and the railway corridor (adjacent to Morgan Street). If a feasible option is available, the consultant will then prepare concept design drawings and bill of quantities.

Northern Beaches Council

Narrabeen Lagoon entrance clearance project

North Narrabeen Lagoon is classified as an intermittently open and closed lagoon, where wave activity and ocean tides cause sand to infill and periodically close the narrow channel entrance. This natural build-up of sand significantly increases the risk of flooding in the floodplain surrounding the lagoon.

This project involves the extraction of up to 30,000 cubic metres of sand from the lagoon entrance and placing it on Collaroy-Narrabeen Beach. This action reduces flood risk by improving hydraulic efficiency, reducing the shallow water effect and friction caused by an infilled lagoon entrance.

The Narrabeen Lagoon entrance clearance project will reduce flood risk for approximately 2,066 properties, as well as public assets and essential infrastructure within the highly urbanised floodplain surrounding Narrabeen.

Queanbeyan-Palerang Regional City Council

Bungendore overflow channel

This project involves the construction of an overflow channel that will pass under Tarago Road on Turallo Creek in Bungendore; this is one of 3 physical flood mitigation measures proposed in the Bungendore floodplain risk management study and plan.

This channel will allow floodwaters to bypass the Tarago Road bridge crossing of the creek during flood events. The higher flows will be diverted across Tarago Road upstream of the bridge crossing, so that they will re-enter the creek downstream of the confluence of Turallo and Halfway creeks, directing flood waters away from properties in the Bungendore town centre.

The channel will also provide flood storage during major events, decreasing the flood impact on nearby properties.

Shellharbour City Council

Jock Brown detention basin – detailed design

The project involves design and environmental approvals for a detention basin in the northern part of the Elliot Lake-Little Lake catchment. The Elliot Lake-Little Lake floodplain risk management study and plan identifies 4 locations where a basin would be suitable, including Jock Brown Oval reserve, as a mitigation measure with a medium priority.

Tweed Shire Council

Murwillumbah central business district levee spillway upgrade – detailed design

In both 2017 and 2022 floods, the Murwillumbah central business district (CBD) levee suffered overtopping across the earthen section of the levee, which is prone to scour failure. A scour failure of the earthen levee has the potential to unleash a flood wave into the Murwillumbah CBD, which would have a significant impact on the town.

The Murwillumbah CBD levee and drainage study (2018) recommended the installation of a formalised spillway to achieve safe and controlled overtopping of the levee during events equal to or greater than the levee crest. Council has completed preliminary flood modelling, survey, and geotechnical investigation to facilitate a spillway upgrade of the earthen section of levee.

This project will complete a detailed design of a spillway and associated reconfiguration of the earthen section of the Murwillumbah CBD flood levee.

Upper Hunter Shire Council

Aberdeen levee rehabilitation

This project will undertake a feasibility and option analysis to rehabilitate the Aberdeen levee, a crucial piece of infrastructure protecting the township from flood-related risks. It functions as a deflector levee and shields against smaller floods (up to the 50-year average recurrence interval) and redirects high-velocity flows during larger floods, safeguarding the township.

The project will assess the feasibility of various options to rehabilitate the levee; encompassing engineering assessments, environmental impact studies and stakeholder engagement.

Wollongong City Council

Ursula Road flood mitigation scheme (stage one – high priority): construction

The Collins Creek floodplain risk management study and plan (2014) proposed various mitigation measures, including the Ursula Road flood mitigation scheme. This scheme involves constructing levees and swales to mitigate flooding.

A detailed investigation and concept design of the scheme identified levees at Franklin Avenue, Spinners Way and Benelong Street as high priority (stage one) projects. These levees offer the most significant hydraulic benefits across the largest number of properties between Franklin Avenue and Trinity Row.

This project will complete stage one of the scheme and result in flood level reductions across private residential properties as well as the Waniora Public School and Bulli High School and several public local roads.

2022–23

Funding for these projects came from the Australian Government's Emergency Response Fund. 

The NSW Flood Recovery and Resilience Grant Program funded 19 projects totalling $20,841,140.

Overview
Grant recipient/local government areaProject nameFunding
Bayside CouncilSeaforth Park detention basin detailed design$135,000
Bellingen Shire CouncilLavenders Bridge replacement – investigation and design$365,000
Byron Shire CouncilBillinudgel rail bridge debris options study and implementation$175,000
Clarence Valley CouncilPenstock valves – Grafton and South Grafton$50,000
Georges River CouncilDetailed feasibility study – Gloucester Road, Stoney Creek Road and Morgan Street$135,000
Northern Beaches CouncilNarrabeen Lagoon entrance clearance project 2025$1,125,000
Queanbeyan-Palerang Regional CouncilBungendore overflow channel$2,250,000
Shellharbour City CouncilJock Brown detention basin – detailed design$135,000
Tweed Shire CouncilMurwillumbah central business district levee spillway upgrade – detailed design$135,000
Upper Hunter Shire CouncilAberdeen levee rehabilitation$105,000
Wollongong City CouncilUrsula Road flood mitigation scheme (stage one – high priority): construction$742,500
Project summaries

Bayside Council

Seaforth Park detention basin detailed design

This project involves a feasibility investigation and preparation of a detailed design that will result in construction ready drawings for the Seaforth Park detention basin in the Muddy Creek catchment, as recommended in the Bayside west floodplain risk management study and plan.

The proposed basin will be a tiered configuration, with a total capacity of 5,000 cubic metres. It will reduce flooding in a number of properties along its 500-metre flow path.

Bellingen Shire Council

Lavenders Bridge replacement – investigation and design

This project will encompass investigation and design for a replacement of Lavenders Bridge in Bellingen. Lavenders Bridge crosses the Bellinger River and connects South Bellingen and North Bellingen. The existing Lavenders Bridge is a timber/concrete composite bridge that is regularly overtopped by flood water.

This project will involve assessing replacement options, a detailed survey, geotechnical investigation, preliminary design drawings, a construction bill of quantities and cost estimate of the preferred configuration.

Byron Shire Council

Billinudgel rail bridge debris options study and implementation

This project will undertake an options study for debris control measures for the Billinudgel railway bridge. This action is a high priority within the North Byron floodplain risk management plan. The options study will include potential infrastructure improvements and recommended solutions.

Clarence Valley Council

Penstock valves – Grafton and South Grafton

Penstocks are one element of critical infrastructure that prevents flooding in Grafton and there are 24 penstock valves.

Council relies on staff that reside in Grafton to access this flood prevention infrastructure, to provide the required assistance during flood events. It currently takes 4 staff over an hour to shut one penstock, using a large heavy metal wheel.

This project aims to modernise, provide efficiencies and increase safety to the process of shutting penstocks, by installing motorised actuators on them. This will enable activation by pressing a button to close the penstocks.

Georges River Council

Detailed feasibility study – Gloucester Road, Stoney Creek Road and Morgan Street

In 2023, Georges River Council completed an overland flow floodplain risk management study and plan, which covers Gloucester Road, Stoney Creek Road and Morgan Street at Beverly Hills. The community in these areas experienced significant flooding in 2021 and 2022.

This project involves a detailed feasibility study of the option to augment the drainage culverts under Stoney Creek Road and the railway corridor (adjacent to Morgan Street). If a feasible option is available, the consultant will then prepare concept design drawings and bill of quantities.

Northern Beaches Council

Narrabeen Lagoon entrance clearance project

North Narrabeen Lagoon is classified as an intermittently open and closed lagoon, where wave activity and ocean tides cause sand to infill and periodically close the narrow channel entrance. This natural build-up of sand significantly increases the risk of flooding in the floodplain surrounding the lagoon.

This project involves the extraction of up to 30,000 cubic metres of sand from the lagoon entrance and placing it on Collaroy-Narrabeen Beach. This action reduces flood risk by improving hydraulic efficiency, reducing the shallow water effect and friction caused by an infilled lagoon entrance.

The Narrabeen Lagoon entrance clearance project will reduce flood risk for approximately 2,066 properties, as well as public assets and essential infrastructure within the highly urbanised floodplain surrounding Narrabeen.

Queanbeyan-Palerang Regional City Council

Bungendore overflow channel

This project involves the construction of an overflow channel that will pass under Tarago Road on Turallo Creek in Bungendore; this is one of 3 physical flood mitigation measures proposed in the Bungendore floodplain risk management study and plan.

This channel will allow floodwaters to bypass the Tarago Road bridge crossing of the creek during flood events. The higher flows will be diverted across Tarago Road upstream of the bridge crossing, so that they will re-enter the creek downstream of the confluence of Turallo and Halfway creeks, directing flood waters away from properties in the Bungendore town centre.

The channel will also provide flood storage during major events, decreasing the flood impact on nearby properties.

Shellharbour City Council

Jock Brown detention basin – detailed design

The project involves design and environmental approvals for a detention basin in the northern part of the Elliot Lake-Little Lake catchment. The Elliot Lake-Little Lake floodplain risk management study and plan identifies 4 locations where a basin would be suitable, including Jock Brown Oval reserve, as a mitigation measure with a medium priority.

Tweed Shire Council

Murwillumbah central business district levee spillway upgrade – detailed design

In both 2017 and 2022 floods, the Murwillumbah central business district (CBD) levee suffered overtopping across the earthen section of the levee, which is prone to scour failure. A scour failure of the earthen levee has the potential to unleash a flood wave into the Murwillumbah CBD, which would have a significant impact on the town.

The Murwillumbah CBD levee and drainage study (2018) recommended the installation of a formalised spillway to achieve safe and controlled overtopping of the levee during events equal to or greater than the levee crest. Council has completed preliminary flood modelling, survey, and geotechnical investigation to facilitate a spillway upgrade of the earthen section of levee.

This project will complete a detailed design of a spillway and associated reconfiguration of the earthen section of the Murwillumbah CBD flood levee.

Upper Hunter Shire Council

Aberdeen levee rehabilitation

This project will undertake a feasibility and option analysis to rehabilitate the Aberdeen levee, a crucial piece of infrastructure protecting the township from flood-related risks. It functions as a deflector levee and shields against smaller floods (up to the 50-year average recurrence interval) and redirects high-velocity flows during larger floods, safeguarding the township.

The project will assess the feasibility of various options to rehabilitate the levee; encompassing engineering assessments, environmental impact studies and stakeholder engagement.

Wollongong City Council

Ursula Road flood mitigation scheme (stage one – high priority): construction

The Collins Creek floodplain risk management study and plan (2014) proposed various mitigation measures, including the Ursula Road flood mitigation scheme. This scheme involves constructing levees and swales to mitigate flooding.

A detailed investigation and concept design of the scheme identified levees at Franklin Avenue, Spinners Way and Benelong Street as high priority (stage one) projects. These levees offer the most significant hydraulic benefits across the largest number of properties between Franklin Avenue and Trinity Row.

This project will complete stage one of the scheme and result in flood level reductions across private residential properties as well as the Waniora Public School and Bulli High School and several public local roads.